Purpose

This walk-through plan produces a complete, defensible loss path and electronics scope on a lightning loss in a single site visit. Follow the phases in order. Do not allow anyone to power on or test devices until Phase 5 is complete and dispositions are recorded.

⚠ Critical Rule
No device in the loss path is powered on, tested, or unplugged until the loss path is documented and inventory dispositions are tiered. Powering a surge-exposed device can complete latent damage and compromise scope defensibility.

Time Budget Summary

PhaseActivityTime
0Pre-Arrival (Office)15–20 min
1Insured Interview & Site Briefing10–15 min
2Exterior Walk & Entry Point ID15–25 min
3Electrical System Inspection20–30 min
4Low-Voltage and Bonded Systems15–20 min
5Room-by-Room Inventory60–120+ min
6Loss Path Synthesis (on-site)15–20 min
7Removal, Pack-Out, Chain of CustodyVariable
8Post-Visit (Office)60–90 min
TotalTypical residential direct strike, on-site portion2.5–4.5 hours

Roles & Responsibilities

RoleOn Lightning Loss
PM (Jack)Owns loss path narrative, insured communication, scope defensibility, carrier interface
Site Lead (Finn)Coordinates field execution, ensures phases run in order, owns photo completeness
Field Tech (Edward / Christian / Genesis / Joey)Executes inventory, photographs, low-voltage and electrical observations, removal
Revenue Integrity (Sam)Translates loss path and inventory into Xactimate scope with F9 notation; submits via XactAnalysis
Warehouse / Fleet (Tony)Coordinates transport of Tier 2 items to facility
Production (Carlos)Receives Tier 2 items, stages for bench evaluation
Electronics Lead (Dunia / Noemi / Nora)Bench evaluation, disposition reports, inspection findings for carrier file